PROGRESS AND TIMEFRAME
Start of the Project: 1 October 2004 End of the Project: 31 March 2007
Duration: 30 months
Current status: Phase VI (adaptation)
Phase I: Project Start, October to December 2004
- Creation of optimal conditions for project work in the following phases
Phase II: Activation and basic theoretical work / start of model development, January 2005 to April 2005 (4 months)
- Contextualising and focusing of the potential project target groups in all countries involved
- Creation of a theoretical basis for the model development
- Beginning of model development work
Phase III: Model and Product Development, May to October 2005 (6 months)
- Creation of job profiles and standards for experts in digital media design and production
- Agreeing the provisional evaluation model for the job and qualification profiles
- Beginning of work on the project curricula
Phase IV: Continuing project development, public relations and interim evaluation, November 2005 to March 2006 (5 months)
- Continuing development of the curricula
- Dissemination of information on the current stage of the project work
- Public Relations to recruit participants of the pilot events for testing of the materials & models
- Summary of the current project results, evaluation and interim reports
Phase V: Certification Model, Model- and Product Testing/Pilot Events, April to August 2006 (5 months)
- Devising the Certification Model
- Realisation of selected parts of the established materials/models
- Monitoring of the practicability of the established materials/models
- Feedback regarding possible changes
Phase VI: Adaptation/Expansion of the Models, September to December 2006 (4 months)
- Continuing of the pilot phase
- Inclusion of the results of the trial phase into the final work on the materials and models
- Finalising the model for European job and qualification profiles, and standards for measuring continuing education in the field of digital media design and production
Phase VII: Further transnational dissemination of the project results and products and final evaluation, January to March 2007 (3 months)
- Final sustained dissemination of all project results and products on a regional, national, and transnational basis
- Summary of the project results
- Final evaluation and writing the final report
|
|
This project has been funded with support from the European Commission.
|
|